40-Mile Source to Frac Project

Scroll Down
Large-Scale Water Management for Multi-Well Completion Project
Overview

Tackling a Massive Water
Management Challenge

A hydraulic fracturing operation in the Permian Basin whose water is managed by Flowpoint.
Flowpoint successfully executed a comprehensive water management solution for a complex 12-well completion project, demonstrating our capability to handle large-scale operations with efficiency and precision.
7M+
Barrels of Water Supplied
25
water transfer pumps strategically along the route
40
Miles of lay-flat hose installed
* Add any required disclaimer text for the claims made above using this small fine-print text.
Key Challenges

Navigating Logistical Complexities

Water Volume Management
Aggregating and managing a massive volume of 7 million barrels of water.
Permitting and Land Access
Securing necessary landowner Right of Way (ROW) and permits.
Long-Distance Water Transportation
Transporting water over long distances to multiple locations.
High-Rate Simultaneous Water Transfer
Maintaining consistent high-rate water transfer to two simultaneous frac fleets.
Ensuring Continuous Operations
Ensuring zero downtime throughout the project duration
Our Solutions
Water Sourcing and Logistics
  • Aggregated 7 million barrels of water from various sources
  • Secured all required landowner ROW and permits for water transportation
  • Established a centralized pit 20 miles from the source location
  • Water Transfer Infrastructure
  • Installed over 40 miles of lay flat hose
  • Deployed 25 water transfer pumps strategically along the route
  • High-Volume Water Delivery
  • Supplied two frac fleets simultaneously
  • Maintained a consistent flow rate of 120 barrels per minute to each pad location
  • Successfully transferred water to pad locations 4 miles away from the centralized pit
  • Automation and Safety
  • Implemented our proprietary automation system across all 12 wells
  • Ensured safe and adequate water distribution from source to frac sites
  • Achieved zero downtime throughout the entire project
  • Workforce Optimization
  • Staffed the project with 5 trained water technicians per shift
  • Reduced ordinary labor demand by approximately 66%
  • Results and Benefits
  • Operational Efficiency: Flawless Execution with Zero Downtime
  • Cost Savings: Significant Labor Cost Reduction Through Smart Staffing
  • Environmental Stewardship: Minimizing Water Waste and Environmental Impact
  • Safety Excellence: Ensuring Risk-Free Operations with Advanced Automation
  • Conclusion

    This case study demonstrates Flowpoint's ability to deliver comprehensive, efficient, and reliable water management solutions for large-scale energy projects. By leveraging our advanced technology, skilled workforce, and innovative approaches, we successfully overcame complex logistical challenges, optimized resource utilization, and ensured uninterrupted operations for our client. This project serves as a testament to our commitment to excellence and our capacity to handle the most demanding water management needs in the energy sector.
    Contact Flowpoint

    Connect With Us

    Make Flowpoint your first call for solving your water challenges and revolutionizing your oilfield water management.
    Thank you, we have received your request and will be in touch shortly.
    Oh no! Something went wrong while submitting the form. Please try again.
    * Add any required disclaimer text for the claims made above using this small fine-print text.
    A Flowpoint truck driving along water transfer infrastructure